top of page

Norman Griffiths Oval Update




April 26

Ku-ring-gai Council has provided a further update on the Norman Griffiths Oval redevelopment, including a revised timeline and progress on key project elements.

revised timeline and progress on key project elements.

Project Overview

Council confirmed in September 2025 that the project will be completed with a synthetic turf playing surface.


The full upgrade includes:


  • Synthetic playing field with a 2.4ML underground stormwater detention system

  • New field lighting

  • Fencing and pathways

  • Landscaping works

  • Electronic scoreboard

  • Replacement of the sewer main beneath the site


Current Status


The project is currently in the design, approvals and procurement phase, with construction yet to recommence.


Council has engaged NSW Public Works to provide independent project assurance, and additional work has been required to finalise key elements of the design — particularly around stormwater management and environmental controls.


Recent Progress

Since the previous update, Council has advised that the following work has been undertaken:


  • NSW Public Works appointed to provide independent oversight

  • Design review of the stormwater detention system

  • Review of synthetic turf specifications

  • Approval received from Sydney Water for sewer main replacement

  • Tender process commenced for sewer works

  • Environmental documentation updated and to be publicly exhibited


Following the transition from the previous contractor, Council has also undertaken works to secure and stabilise the site.


Site Management & Environmental Controls

Significant improvements have been made to environmental management, including:


  • Enhanced stormwater capture, storage and treatment systems

  • Improved erosion and sediment controls in line with EPA requirements

  • Reduced need to remove water from site during heavy rain events


The site is monitored daily for environmental compliance, safety and cleanliness.

During rainfall, water is stored, treated, tested and only released once it meets strict EPA standards.


Water Quality Monitoring

Stormwater released from the site must meet EPA guidelines, including:


  • pH: 6.5 – 8.3

  • Turbidity: less than 30 NTU

  • Salinity: less than 1.8

  • No visible pollutants


Water quality in Quarry Creek continues to be independently monitored, with results published by Council.


It is also important to note that stormwater entering Quarry Creek comes from the broader catchment area, not just the construction site.


Updated Delivery Timeline


Council has outlined the following indicative program:


Design & Approvals

  • Design completion: June 2026

  • Environmental (REF) approval: June 2026

  • Sydney Water approvals: completed February 2026


Procurement & Preparation

  • Sewer main upgrade works: through to September 2026

  • Main construction tender: July 2026

  • Council approval to award contract: August 2026


Construction & Access

  • Construction completion: February 2027

  • Field open for community use: February 2027


Final Completion

  • Full project completion (including contingency): May 2027


Key Considerations

Council has advised that the program includes limited contingency, and a number of factors may still impact delivery, including:


  • Contractor availability

  • Supply chain delays

  • Environmental approvals

  • Weather conditions


The project remains technically complex, particularly due to stormwater management requirements and the proximity to Quarry Creek.


What This Means

The project has now moved from a paused and uncertain position to a more structured and independently reviewed program. However, additional design and approval work has extended the overall timeline.


Construction is now expected to recommence later in 2026, with the field anticipated to return to use in early to mid 2027.


From the Club

We know how important Norman Griffiths Oval is to our players, families and the broader community, and we share the frustration around the delays.


It is encouraging to see progress being made and a clearer pathway to completion now in place. We will continue to keep our members updated as further information becomes available.




 
 
WEST-PYMBLE-LOGO-WHITE-CENTRE.png

Norman Griffiths Oval

Lofberg Road,

West Pymble NSW 2073

Mail: 40/12 Philip Mall
Kendall Street,

West Pymble NSW 2073

© Copyright 2025 West Pymble FC

NSFAColourLogo_edited_edited.png

Privacy Policy

bottom of page